Trust Power Patearoa Project

AIE Hydro successfully completed the project to manufacture an improved turbine to give the machine controllability across a larger range of flow rates and thereby gaining additional output of 2.5GW/h per year from the new machine.

The manufacturing time was 4 months, with 5 weeks of installation and commissioning work. This was almost a month ahead of schedule and provided additional unbudgeted earnings for the customer.